HYDRAULIC ANALYSIS OF THE SEWERAGE SYSTEM OF THE SETTLEMENT OF DEC
DOI:
https://doi.org/10.24867/13CG10RadlovicKeywords:
Hydraulic analysis, sewage network, software program SWMM 5.1., purification deviceAbstract
With this project task, a hydraulic analysis of the sewage system of the settlement of Deč in the municipality of Pećinci was done. The analysis of the planned sewerage system was done on the basis of the already existing Preliminary design. By analyzing the planned sewage system od the Deč settlement, we defined the loads of the system by nodes and sections. We used the SWMM 5.1 software program for analysis. The planned sewerage system of the Deč settlement consists of gravity sewerage collectors with connections, with a total length of about 14,000.00 m. Due to the predominantly flat terrain and large burial depths, four pumping stations are envisaged ("ЦС1", "ЦС2", "ЦС3", "ЦС4"). All wastewater from the settlement of Deč is pumped to the water purification device in the settlement of Šimanovci (UPOV).
References
Hidrotehnika, deo 2, Fakultet tehničkih nauka u Novom Sadu, 2017
[2] Studija o proceni uticaja glavnog projekta postrojenja za prečišćavanje otpadnih voda za naselje Šimanovci na k.p.br. 2510/2 K.O.Šimanovci na životnu sredinu, Fakultet Tehničkih Nauka, Novi Sad
[3] Izmene i dopune Plana generalne regulacije naselja Deč ("Sl. list Srema"br.29/2012 i 8/2014)
[4] Hajdin Georgije: Mehanika fluida knjiga prva Uvođenje u hidrauliku, Građevinski fakultet, Beograd, 2002
[5] SWMM 5.0 User's manual 2010