CONSTRUCTION OF THE MAIN-MAGISTRAL CHANNEL OROM-ČIK-KRIVAJA SUBSYSTEM TISA-PALIĆ, REPUBLIC OF SERBIA
DOI:
https://doi.org/10.24867/01CG04KurcubicKeywords:
construction technology, Orom-Čik-Krivaja channelAbstract
The subject of work is planning and organizing perform of channel profile on II section of magistral channel Orom-Čik-Krivaja from the km 9+450 to km 24+450. This implies planning the process of technologies of the excavation and the profile of the embankment, the selection of the appropriate anti-filtration coating, as well as the selection of the appropriate mechanization.
References
[1] Studija opravdanosti i studije uticaja na životnu sredinu magistralnog kanala Orom-Čik-Krivaja (deonica II) podsistema Tisa-Palić.
[2] Mehanizacija u građevinarstvu, Ratko S. Ćulibrk, Momir M. Plavšić, Univerzitet u Novom Sadu, Građevinski fakultet u Subotici, 2007. godine.
[3] Tehnologija i organizacija građenja, Milan Trivunić, Zoran Matijević, FTN izdavaštvo, Novi Sad, 2009. godine.
[2] Mehanizacija u građevinarstvu, Ratko S. Ćulibrk, Momir M. Plavšić, Univerzitet u Novom Sadu, Građevinski fakultet u Subotici, 2007. godine.
[3] Tehnologija i organizacija građenja, Milan Trivunić, Zoran Matijević, FTN izdavaštvo, Novi Sad, 2009. godine.
Downloads
Published
2018-12-21
Issue
Section
Civil Engineering