Civil Engineering

Vol. 41 No. 10 (2026): Proceedings of the Faculty of Technical Sciences

Comparative Analysis of Time Efficiency in Traditional and BIM Technical Documentation Approaches

  • Марко Шуњевић
DOI:
https://doi.org/10.24867/36CG09Sunjevic
Submitted
October 14, 2026
Published
2026-10-16

Abstract

The research presented in the paper was conducted through a comparative analysis of the time efficiency of technical documentation development using two approaches: the traditional 2D method and BIM methodology. The key elements of the research were examined through a case study based on the same building project and identical design requirements. The analysis included the time required for the preparation of graphical documentation, structural calculations, implementation of design modifications, and final documentation review. The results indicate that the BIM approach enables a significant reduction in the time required for technical documentation development, particularly during the revision and project coordination phases. Furthermore, the study confirmed that an integrated digital model represents an effective tool for improving productivity and reducing the risk of errors throughout the design process.

References

  1. [1] N. Bredella, “Simulation and Architecture: Mapping
  2. Building Information Modeling,” NTM Zeitschrift für
  3. Geschichte der Wissenschaften, Technik und Medizin,
  4. vol. 27, no. 4, pp. 419–441, Dec. 2019, doi:
  5. 10.1007/s00048-019-00224-9.
  6. [2] B. C. Matos, C. O. Cruz, and F. Branco,
  7. “Digitalization and procurement in construction
  8. projects: An integrated BIM-based approach,” Journal
  9. of Information Technology in Construction, vol. 29,
  10. pp. 400–423, May 2024, doi:
  11. 10.36680/j.itcon.2024.019.
  12. [3] A. Borrmann, M. König, C. Koch, and J. Beetz, Eds.,
  13. Building Information Modeling: Technology
  14. Foundations and Industry Practice. Cham: Springer
  15. International Publishing, 2018, doi: 10.1007/978-3-
  16. 319-92862-3.
  17. [4] Z. Pučko, N. Šuman, and U. Klanšek, “Building
  18. Information Modeling Based Time and Cost Planning
  19. in Construction Projects,” Organization, Technology
  20. and Management in Construction: An International
  21. Journal, vol. 6, no. 1, 2014, doi:
  22. 10.5592/otmcj.2014.1.6.
  23. [5] U. Isikdag, “Building Information Models: An
  24. Introduction,” in Enhanced Building Information
  25. Models, ser. SpringerBriefs in Computer Science.
  26. Cham: Springer International Publishing, 2015, pp. 1–
  27. 12, doi: 10.1007/978-3-319-21825-0_1.
  28. [6] Ž. Ljevo, M. Pozder, S. Sulejmanović, S. Albinović,
  29. A. Šarić, and A. Borić, “Enhancing Construction
  30. Project Management Using BIM,” in Advanced
  31. Technologies, Systems, and Applications X, ser.
  32. Lecture Notes in Networks and Systems, vol. 1625, N.
  33. Ademović, Z. Akšamija, and A. Karabegović, Eds.
  34. Cham: Springer Nature Switzerland, 2026, pp. 435–
  35. 446, doi: 10.1007/978-3-032-05159-2_27.